How to connect - Larger systems over 30kVA

Distributed Energy Resource (DER) systems can help manage your demand on our electricity network during peak times and assist in the event of emergency outages or power supply interruptions.

These can be DER systems such as:

  • Bumpless or parallel systems via rotating machines (i.e. diesel)
  • Exporting systems via renewable energy technology such as solar, battery, wind and biogases.

These DER systems usually benefit from the Australian Energy Market Operator's (AEMO) standing exemption and are required to follow the connection process under Chapter 5A of the NER.

Our Network Load Capacity Map shows details about the local electricity network, including historical load, the amount of generation connected and the capacity of network assets.

Whilst all individual connection applications are subject to our normal connection assessment processes, this may provide a general indication of whether a site may have particular export restrictions applied.

How to apply for connection

Use the Enquiry Form in the Electrical Partners Portal to start the connection process.

As part of the connection process, we’ll check if the local electricity network can support your proposed system to work effectively. We’ll also need to establish a connection contract with you.

Further information on the connection process is available in Part A of our Embedded Generation Information Pack (PDF 1.6 mb). The following information explains the types of connections.

Basic connection

If your connection qualifies as a basic connection service according to our Connection Policy (PDF 685.0 kb), our Model Standing Offer (PDF 1.1 mb) explains the applicable conditions for connecting your DER system to our electricity distribution network.

Negotiated connection

Where your connection does not qualify as a basic connection service, or you choose to negotiate the terms of your connection contract, you can negotiate your connection offer with us according to the National Electricity Rules framework. Please refer to our Negotiated Connection Agreement (PDF 456.9 kb) for our indicative terms.

Connection contract

Under the National Electricity Rules, when we receive a connection application we must make an offer to the applicant to enter into a connection contract. Your connection contract will commence when you accept our connection offer.

Important information for generators

The latest versions of the Embedded Generating Connection Standards came into effect from 23 February 2025. For more information about this change, please read our FAQs (see link below).

FAQs for Solar Installers

Check out our frequently asked questions about solar connections, standards and technical matters.

Relevant documents

Get in touch

Do you have a specific question about connecting an embedded generator? If so, please contact our Solar and Renewables Team at ergongeneration@energyq.com.au.