Note
Grayed out layers are only available at certain zoom levels.
Note
- Data applies to the current year only. Data will be updated annually in line with the release of the Distribution Annual Planning Report (DAPR).
- Some data layers may need to be enabled, or are only available at certain zoom levels. Please see for Layer options
About this map
This mapping portal forms part of our Distribution Annual Planning Report (DAPR) (.pdf) and presents:
- the topology of our regulated network, including transmission network connection points, substations, sub-transmission network and distribution feeders.
- forecast loads for transmission network
- connection points, forecast loads and capacity information for each of our substations and sub-transmission feeders
- distribution feeders that are forecast to have capacity constraints in the next 2 years
- substation constraints that are forecast to emerge in the next 5 years
As a Distribution Network Service Provider (DNSP), we are required to publish this information under Rule 5.13 and Schedule 5.8 of the National Electricity Rules (NER).
FORECAST INFORMATION
The subtransmission line tables include the following information:
-
Planning Region
- Ergon Energy Ecorp Asset ID
- Ergon Energy operational number
- Subtransmission line description
-
Summer capacity & load forecasts for 5 years
- Rating (Amps)
- Loading (Amps)
- Power Factor
Definitions
SD: Summer Day (9am to 5pm)
SE: Summer Evening (5pm to 10pm)
SNM: Summer Night/Morning (10pm to 9am)
Summer: December to March
Comments
-
Poor power factors of some feeders
Where the power factors are very low it is because (in general) the feeder is part of a ring network with circulating reactive power. The active power is swamped by the reactive power in these cases. There are some radial feeders where the power factor is also very low. This is as a result of very little active power being supplied by these feeders combined with a lot of line charging reactive power which once again swamps the active power component. -
Missing power factors
This is a result of unloaded feeders that are only energised from one side. There is some line charging which accounts for the non-zero loading in amperes but there is no active power supplied by the feeder.
The Substation Forecast file has information on 5-year forecast capacity and loading information for each Ergon Energy owned Bulk Supply and Zone Substations.
Definitions
Peak Risk Period: The time period over which the load is highest (Summer/Winter).
NCC Rating (MVA): Normal Cyclic Capacity - the total capacity with all network components and equipment in service.
Contracted non-network (MVA): The amount of embedded generation and contracted curtailed demand management capacity available within the supply area of a substation during peak times. The impacts of these have been incorporated into the load forecasts. Solar PV connections are not included in the reported figure.
10 PoE Load (MVA): Peak load forecast with 10% probability of being exceeded (one in every 10 years will be exceeded). Based on normal expected growth rates and weather corrected starting loads.
LARn (MVA): Security standard load at risk under system normal condition, expressed in MVA.
LARn (MW): Security standard load at risk under system normal condition, expressed in MW.
Power Factor at Peak Load: Compensated power factor at 50 PoE Load.
ECC Rating (MVA): The maximum permissible peak emergency loading for a given load cycle that an item of plant can supply for an extended period of time without unacceptable damage. For substations with multiple transformers, the ECC is the minimum emergency cyclic capacity of all transformer combinations taking impedance mismatches into consideration, with one transformer offline.
50 PoE Load (MVA): Peak load forecast with 50% probability of being exceeded (one in every two years will be exceeded). Based on normal expected growth rates & weather corrected starting loads.
Hours PA > 95% Peak Load: The amount of load greater than 95% 50 PoE Load.
Raw LAR (MVA): The amount of load exceeding ECC rating. (Load – ECC Rating)
Auto Trans Avail (MVA): SCADA or automatically controlled load transfers that can be implemented within one minute.
Remote Trans Avail (MVA): Load transfers that can be implemented through SCADA switching procedures by the network control officer. It is assumed that this can generally be achieved within 30 minutes.
Manual Trans Avail (MVA): Load transfers can also be deployed via manually controlled switchgear locally by field staff.
Mobile Plant Avail (MVA): The capacity of mobile substation or mobile generation that can be deployed within the timeframe and capacity prescribed by the security standard.
Shed(30min): Loads to large customers which can be disconnected by remote operation of switchgear.
Shed(4Hour): Loads to large customers which need manual switching by field crews to disconnect them from the network.
Capacity for Embedded Generation(MVA): The total capacity for embedded generation to transfer power from lower voltage network to higher voltage network with all network components and equipment in service.
Firm Capacity for Embedded Generation (MVA): The firm capacity for embedded generation to transfer power from lower voltage network to higher voltage network under a single contingent condition.
LARc (MVA): Security standard load at risk for single contingent conditions.
LARc (MW): Estimated generation / load reduction required to defer the forecast system limitation. This is the security standard load at risk under single contingency condition, expressed in MW.
Substation Category: For security standard application, the general type of customer a substation or feeder supplying the area.
For further information, please refer to Appendix D of Ergon Distribution Annual Planning Report.
The Transmission Connection Point Forecasts include the following information for 50 PoE and 10 PoE in summer and winter:
- Ergon Energy region
- TNI: National Electricity Market - Transmission Node Identity
- TCP Name: Name of the Transmission Connection Point
- Forecast Peak Load (MW)
- Forecast Peak Load (MVARu) (VARu = Volt Amps Reactive Uncompensated, i.e. with stated compensation not active)
- Forecast Compensation (MVAR)
Exclusions
Forecast capacity is not
given this spreadsheet. In the majority of cases, the
capacity at the TCP is controlled by the Transmission
Network Service Provider, and hence reported by them. In the
relatively few cases where Ergon Energy asset boundary at
the TCP is inclusive of power transformers, the substation
capacity will appear in the Zone or Bulk Supply Substations
Forecasts tables. The forecast loads are given exclusive of
any connected embedded generation.
The Distribution Feeder Limitations tables include the following information for each constrained distribution feeder:
- Ergon Energy region
- Distribution feeder name, ID & location
- Load exceedance after 2 yrs (MVA)
- Forecast season that exceedance occurs (Summer / Winter)
- Forecast year that exceedance occurs
- Forecast month/s that exceedance occurs
- Load reduction needed to delay the exceedance by 12 months (MW) (assumed power factor of 0.9)
Solutions
Suggested solutions, in
order or preference, are included under the 'Solutions' tab.
Connection points for possible load reduction
In all cases,
the connection point to apply load
reduction would be downsteam of the substation exit feeder
cable and/or first section of line.
Exclusions
Dedicated customer
connection assets are excluded from the analysis.
GENERAL INFORMATION
Disclaimer
The DAPRM (Distribution Annual Planning Report Map) is an interactive geospatial map that has been developed to provide indicative information regarding Ergon Energy’s regulated network topology, forecast loads and capacities, and network constraints. The DAPRM is an information service available to the public.
Users of this service must acknowledge and accept that:
- The information obtained from the DAPRM is intended as general in nature, may be based on assumptions that change with time and may not necessarily be complete. Information contained in, or obtained from, the DAPRM should not be relied upon.
- Ergon Energy makes no representation or warranty as to the accuracy or completeness of any information obtained from the DAPRM. The DAPRM is not a substitute for independent advice and research.
- Ergon Energy does not accept any responsibility for any loss or damage, however caused, which any person or entity may suffer in connection with the information contained in, or obtained from, the DAPRM.